ANNEXE 18
CE QU' A COUTE LE PROGRAMME APOLLO
| 
         BUDGET NASA  | 
      
         1960  | 
    
| 
         
  | 
      |
| 
         NASA  | 
      523 575 000 | 
| 
         
  | 
      |
| 
         APOLLO  | 
      100 000 | 
| 
         
  | 
      
| 
         BUDGET NASA  | 
      
         1961  | 
    
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      964 000 000 | 
| 
         
  | 
      |
| 
         APOLLO  | 
      1 000 000 | 
| 
         
  | 
      
| 
         BUDGET NASA  | 
      
         1962  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budget original demandé  | 
      
         
  | 
    
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         1 235 300 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         29 500 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budget fiscal  | 
      
         
  | 
    
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         1 671 750 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         160 000 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Vol test en orbite  | 
      
         63 000 000  | 
    
| 
         Vol tests biomédical  | 
      
         16 550 000  | 
    
| 
         Tests de rentré grande vitesse  | 
      
         27 500 000  | 
    
| 
         Développement vaisseaux spatial  | 
      
         52 000 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         BUDGET NASA  | 
      
         1963  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budget original demandé incluant l' année fiscale 1962 en supplément  | 
    |
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         3 787 276 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         617 164 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budget fiscal avec l' année 1963 en supplément  | 
    |
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         3 674 115 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         617 164 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Command et service Module  | 
      
         345 000 000  | 
    
| 
         Lunar Module  | 
      
         123 100 000  | 
    
| 
         Guidage et navigation  | 
      
         32 400 000  | 
    
| 
         Iinstrumentation, équipement scient  | 
      
         11 500 000  | 
    
| 
         Support opérationnel  | 
      
         2 500 000  | 
    
| 
         Développement  | 
      
         3 000 000  | 
    
| 
         Little joe 2 développement  | 
      
         8 000 000  | 
    
| 
         Saturn 1  | 
      
         90 864 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         BUDGET NASA  | 
      
         1964  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budget original demandé incluant l' année fiscale 1963 en supplément  | 
    |
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         3 926 000 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         2 243 900 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budget fiscal avec l' année 1963 en supplément  | 
    |
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         3 974 979 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         2 272 952 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Command et service Module  | 
      
         545 874 000  | 
    
| 
         Lunar Module  | 
      
         135 000 000  | 
    
| 
         Guidage et navigation  | 
      
         91 499 000  | 
    
| 
         Intégration, assemblage et vérifications  | 
      
         60 699 000  | 
    
| 
         Support vaisseaux spatial  | 
      
         43 503 000  | 
    
| 
         Saturn 1  | 
      
         187 077 000  | 
    
| 
         Saturn 1B  | 
      
         146 817 000  | 
    
| 
         Saturn 5  | 
      
         763 382 000  | 
    
| 
         Dévéloppement moteurs  | 
      
         166 000 000  | 
    
| 
         Support mission  | 
      
         133 101 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         BUDGET NASA  | 
      
         1965  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budget original demandé incluant l' année fiscale 1964 en supplément  | 
    |
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         4 523 000 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         2 818 500 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budjet fiscal avec l' année 1964 en supplément  | 
    |
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         4 270 695 00  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         2 614 619 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Command et service Module  | 
      
         577 834 00  | 
    
| 
         Lunar Module  | 
      
         242 600 000  | 
    
| 
         Guidage et navigation  | 
      
         81 038 00  | 
    
| 
         Intégration, assemblage et vérifications  | 
      
         24 763 000  | 
    
| 
         Support vaisseaux spatial  | 
      
         83 663 00  | 
    
| 
         Saturn 1  | 
      
         40 265 000  | 
    
| 
         Saturn 1B  | 
      
         262 696 000  | 
    
| 
         Saturn 5  | 
      
         964 924 000  | 
    
| 
         Dévéloppement moteurs  | 
      
         166 300 000  | 
    
| 
         Support mission  | 
      
         170 542 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         BUDGET NASA  | 
      
         1966  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budget original demandé  | 
      
         
  | 
    
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         4 575 900 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         2 997 385 00  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budget fiscal  | 
      
         
  | 
    
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         4 511 644 00  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         2 967 385 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Command et service Module  | 
      
         615 000 000  | 
    
| 
         Lunar Module  | 
      
         310 800 000  | 
    
| 
         Guidage et navigation  | 
      
         115 000 000  | 
    
| 
         Intégration, assemblage et vérifications  | 
      
         34 400 000  | 
    
| 
         Support vaisseaux spatial  | 
      
         95 400 000  | 
    
| 
         Saturn 1  | 
      
         800 000  | 
    
| 
         Saturn 1B  | 
      
         274 185 00  | 
    
| 
         Saturn 5  | 
      
         1 117 320 000  | 
    
| 
         Dévéloppement moteurs  | 
      
         134 095 000  | 
    
| 
         Support mission  | 
      
         210 385 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         BUDGET NASA  | 
      
         1967  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budget original demandé  | 
      
         
  | 
    
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         4 246 600 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         2 974 200 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budget fiscal  | 
      
         
  | 
    
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         4 175 100 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         2 916 200 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Command et service Module  | 
      
         560 400 000  | 
    
| 
         Lunar Module  | 
      
         472 500 000  | 
    
| 
         Guidage et navigation  | 
      
         76 654 000  | 
    
| 
         Intégration, assemblage et vérifications  | 
      
         29 975 000  | 
    
| 
         Support vaisseaux spatial  | 
      
         110 771 000  | 
    
| 
         Saturn 1  | 
      
         
  | 
    
| 
         Saturn 1B  | 
      
         236 600 000  | 
    
| 
         Saturn 5  | 
      
         1 135 600 000  | 
    
| 
         Dévéloppement moteurs  | 
      
         49 800 000  | 
    
| 
         Support mission  | 
      
         243 900 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         BUDGET NASA  | 
      
         1968  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budget original demandé  | 
      
         
  | 
    
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         4 324 500 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         2 606 500 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budget fiscal  | 
      
         
  | 
    
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         3 970 600 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         2 556 000 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Command et service Module  | 
      
         455 300 000  | 
    
| 
         Lunar Module  | 
      
         329 600 000  | 
    
| 
         Guidage et navigation  | 
      
         113 000 000  | 
    
| 
         Intégration, assemblage et vérifications  | 
      
         66 600 000  | 
    
| 
         Support vaisseaux spatial  | 
      
         60 500 000  | 
    
| 
         Saturn 1  | 
      
         
  | 
    
| 
         Saturn 1B  | 
      
         146 600 000  | 
    
| 
         Saturn 5  | 
      
         998 900 000  | 
    
| 
         Dévéloppement moteurs  | 
      
         18 700 000  | 
    
| 
         Support mission  | 
      
         296 800 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         BUDGET NASA  | 
      
         1969  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budget original demandé  | 
      
         
  | 
    
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         3 677 200 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         2 038 800 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budget fiscal  | 
      
         
  | 
    
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         3 193 559 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         2 025 000 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Command et service Module  | 
      
         346 000 000  | 
    
| 
         Lunar Module  | 
      
         326 000 000  | 
    
| 
         Guidage et navigation  | 
      
         43 900 000  | 
    
| 
         Intégration, assemblage et vérifications  | 
      
         65 100 000  | 
    
| 
         Support vaisseaux spatial  | 
      
         121 800 000  | 
    
| 
         Saturn 1  | 
      
         
  | 
    
| 
         Saturn 1B  | 
      
         41 347 000  | 
    
| 
         Saturn 5  | 
      
         534 453 000  | 
    
| 
         Dévéloppement moteurs  | 
      
         546 400 000  | 
    
| 
         Support mission  | 
      
         
  | 
    
| 
         
  | 
      
         
  | 
    
| 
         BUDGET NASA  | 
      
         1970  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budget original demandé  | 
      
         
  | 
    
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         3 168 900 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         1 651 100 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budget fiscal  | 
      
         
  | 
    
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         3 113 765 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         1 686 145 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Command et service Module  | 
      
         282 821 000  | 
    
| 
         Lunar Module  | 
      
         231 433 000  | 
    
| 
         Guidage et navigation  | 
      
         33 866 000  | 
    
| 
         Charges utiles scientifiques  | 
      
         60 094 000  | 
    
| 
         Support vaisseaux spatial  | 
      
         170 764 000  | 
    
| 
         Saturn 1  | 
      
         
  | 
    
| 
         Saturn 1B  | 
      
         
  | 
    
| 
         Saturn 5  | 
      
         484 439 000  | 
    
| 
         Opération vols habités  | 
      
         422 728 000  | 
    
| 
         Support mission  | 
      
         
  | 
    
| 
         
  | 
      
         
  | 
    
| 
         BUDGET NASA  | 
      
         1971  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budget original demandé  | 
      
         
  | 
    
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         2 606 100 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         956 500 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budget fiscal  | 
      
         
  | 
    
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         2 555 000 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         913 669 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Module de vol  | 
      
         245 542 000  | 
    
| 
         Charges utiles scientifique  | 
      
         106 194 000  | 
    
| 
         Support terrestre  | 
      
         46 411 000  | 
    
| 
         Saturn 5  | 
      
         189 059 000  | 
    
| 
         Opérations vols habités  | 
      
         314 963 000  | 
    
| 
         Developpement avancé  | 
      
         11 500 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         BUDGET NASA  | 
      
         1972  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budget original demandé  | 
      
         
  | 
    
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         2 517 700 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         612 200 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budget fiscal  | 
      
         
  | 
    
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         2 507 700 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         601 200 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Module de vol  | 
      
         55 033 000  | 
    
| 
         Charges utiles scientifique  | 
      
         52 100 000  | 
    
| 
         Support terrestre  | 
      
         31 659 000  | 
    
| 
         Saturn 5  | 
      
         142 458 000  | 
    
| 
         Opérations vols habités  | 
      
         307 450 000  | 
    
| 
         Développement avancé  | 
      
         12 500 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         BUDGET NASA  | 
      
         1973  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budget original demandé  | 
      
         
  | 
    
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         2 600 900 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         128 700 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Budget fiscal  | 
      
         
  | 
    
| 
         
  | 
      
         
  | 
    
| 
         NASA  | 
      
         2 509 900 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         APOLLO  | 
      
         76 700 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         Vaisseaux spatiaux  | 
      
         50 400 000  | 
    
| 
         Saturn 5  | 
      
         26 300 000  | 
    
| 
         
  | 
      
         
  | 
    
| 
         COUT PROGRAMME APOLLO  | 
      Nombre | |
| LAUNCH COMPLEX 39 dont | 1 035 000 000 | |
| Vehicle Assembly Building | 89 000 000 | |
| Equipements intérieur | 63 000 000 | |
| Terrain Merritt Island | 72 000 000 | 64 000 h | 
| Installations au sol | 800 000 000 | |
| Crawler transporter | 11 000 000 | 2 | 
| Saturn 5 | 190 000 000 | 13+3 | 
| Command & Service Module | 55 000 000 | 11+6 | 
| Lunar Module | 40 000 000 | 11 | 
| Lunar Rover Vehicle | 2 000 000 | 3+8 | 
| Station ALSEP | 138 000 000 | 6 | 
| Scaphandres lunaire | 35 000 | |
| Frais de controle | 65 000 000 | |
| COUT GLOBAL | 22 700 000 000 | |
| dont développement lanceur | 9 100 000 000 | |
| Coût mission Apollo 8 | 335 000 000 | |
| Coût mission Apollo 12 | 350 000 000 | |
| Personnel | 26500 | |
| Personnel LCC KSC | 500 | |
| Personnel MCC Houston | 1500 | |
| Radio navires dans le monde | 4 | |
| Avions communication vol | 5 | |
| Stations sol étranger | 13 | |
| Navires en position sur océan | 7 | |
Source Chronologie Apollo NASA publication